Task

Typical length of time

 

Interview architects

2-4 weeks

Appoint architects

4 weeks

Feasibility study

3-6 weeks

Building survey to planning application

4-7 weeks

Planning process

8 weeks

Building control application production

5-7 weeks

Building control process

5 weeks

Preparation of detail drawings

4-6 weeks

Tender process

4 weeks

Lead in time for contractor

4-10 weeks

Construction period

16-20 weeks

Total time

59-81 weeks